MAGIC 

MAGIC Kickoff Meeting Agenda

September 8-9, 1998
San Fernando, Spain

 
Tuesday September 8
10:30 Welcome J. Davila
10:35 Introduction and Meeting Objectives J. Haase
10:40 Introduction of Participants All
10:45 Project Schedule J. Haase
10:50 Individual Partner Schedules (10 minutes each) All
12:15 Coffee Break
12:30 Review of data requirements of DMI for NWP and Climate H. Huang
12:45 Forecast requirements of Catalonia and data requirements of MASS or MM5 L. Cucurull
13:00 Forecast Requirements of Andalusia (if available) J. Davila
13:15 GPS Network Design Discussion E. Calais
Database Structure and access
13:45 Lunch
15:15 GPS Network Design Discussion (continued) E. Calais
Equipment specification - meteo equipment and antennas
15:30 Subgroup discussions
Group 1: Database structure action list E. Calais
Group 2: Customer requirements document J. Haase
16:15 Subgroup summaries
16:30 Break
16:45 Administrative and Organisational Issues (1) J. Haase
17:00 Existing GPS Processing Structure at IEEC A. Flores
17:15 GPS Data Processing Discussion E.Calais
Distributed Processing Structure and Fiducial Network
Processing Methodology and solution format
Quality Control
18:00 Subgroup discussions
Group 1: Processing methodology action list E. Calais
Group 2: Go to the beach
18:30 End of first day
21:00 MAGIC Project Dinner
Wednesday September 9
9:00 GPS IWV Network Validation Test Scenario Discussion E. Calais
10:00 Plan for alternate WV retrieval experiment R. Santangelo
10:20 Status of MASS and MM5 models for Catalonia L. Cucurull
10:40 Status of 3DVAR and 4DVAR development for HIRLAM H. Huang
11:00 Coffee Break
11:15 Verification and Exploitation J. Haase
Templates for objectives and verificatoin report
Exploitation Plan and WWW server
12:30 Administrative and Organisational Issues (2) J. Haase
13:45 Lunch
 
 

Required Input

Each partner: 1 transparency showing short term and long term schedule
ASI, ROA, IEEC, ICC, CNRS: IGS station report for each station to be included in processing for Network status report
Each partner: 1 page describing anonymous ftp site, and where applicable, existing database structure
1 hard copy of presentation material (as detailed in agenda)
(all of the above in electronic form also, where possible)
 
 

Expected Output

Customer Requirements Document
Quality control plan
Network status report
GPS database specification  (Distributed database structure)
Processing Methodology Specification (Distributed processing structure)
GPS IWV validation test scenario definition
Definition of alternate WV retrieval products and users - (OGMO)
 
 
GPS Data  | IWV Data  | Documents | Meetings | Personnel | Admin | Links | Search | Home]



Page last modified 3-Sep-1998
Mail to jh@acri.fr